General Discussion Discuss your Oldsmobile or other car-related topics.

Build date

Thread Tools
 
Search this Thread
 
Old January 25th, 2016, 11:18 AM
  #1  
Bfg
Registered User
Thread Starter
 
Bfg's Avatar
 
Join Date: Jan 2012
Posts: 2,056
Build date

Would a 1965 Cutlass with a build date 04A be considered a early or late build?
Bfg is offline  
Old January 25th, 2016, 11:41 AM
  #2  
Registered User
 
jensenracing77's Avatar
 
Join Date: Feb 2009
Location: Brazil Indiana
Posts: 11,522
About in the middle of the run. week 4 of January.
jensenracing77 is offline  
Old January 25th, 2016, 12:30 PM
  #3  
Old(s) Fart
 
joe_padavano's Avatar
 
Join Date: Mar 2007
Location: Northern VA
Posts: 47,902
Originally Posted by jensenracing77
About in the middle of the run. week 4 of January.
Sorry, you have that bass-ackwards. 04 is the month (April) and A is the week (first week of April). This is not an early car. Production ran late Aug 1964 to July 1965.
joe_padavano is offline  
Old January 25th, 2016, 12:35 PM
  #4  
Registered User
 
TK-65's Avatar
 
Join Date: Feb 2009
Posts: 2,039
Production of 65s ran into the middle of August.
TK-65 is offline  
Old January 25th, 2016, 12:39 PM
  #5  
Old(s) Fart
 
joe_padavano's Avatar
 
Join Date: Mar 2007
Location: Northern VA
Posts: 47,902
Originally Posted by TK-65
Production of 65s ran into the middle of August.
So Sept 64 to early Aug 65? In any case, the OP's car is still an April 65 build.
joe_padavano is offline  
Old January 25th, 2016, 12:46 PM
  #6  
Registered User
 
jensenracing77's Avatar
 
Join Date: Feb 2009
Location: Brazil Indiana
Posts: 11,522
Originally Posted by joe_padavano
Sorry, you have that bass-ackwards. 04 is the month (April) and A is the week (first week of April). This is not an early car. Production ran late Aug 1964 to July 1965.
Wow, I have no idea why I did that. I know better.
jensenracing77 is offline  
Old January 25th, 2016, 12:51 PM
  #7  
Registered User
 
TK-65's Avatar
 
Join Date: Feb 2009
Posts: 2,039
Originally Posted by joe_padavano
So Sept 64 to early Aug 65? In any case, the OP's car is still an April 65 build.
Pretty much. I have some data plates saved from August. I'll have to check when I get home to see what my earliest one is.
TK-65 is offline  
Old January 25th, 2016, 12:56 PM
  #8  
Registered User
 
Koda's Avatar
 
Join Date: Aug 2013
Location: Evansville, IN
Posts: 10,628
I wish we could retool like that now. Very rarely can we shut down for anything more than a holiday week.
Koda is online now  
Old January 25th, 2016, 01:32 PM
  #9  
Old(s) Fart
 
joe_padavano's Avatar
 
Join Date: Mar 2007
Location: Northern VA
Posts: 47,902
Originally Posted by Koda
I wish we could retool like that now. Very rarely can we shut down for anything more than a holiday week.
Yeah, but the annual model changes aren't usually as dramatic as they were in the 60s. They also don't all take place in the summer anymore, either.

Besides, how hard is it to load new software into your assembly robots?
joe_padavano is offline  
Old January 25th, 2016, 02:01 PM
  #10  
Registered User
 
TK-65's Avatar
 
Join Date: Feb 2009
Posts: 2,039
Shutdown was also the time when everyone went on vacation. Mandatory. We don't stop at all now, at least my plant doesn't.
TK-65 is offline  
Old January 25th, 2016, 02:20 PM
  #11  
Registered User
 
Koda's Avatar
 
Join Date: Aug 2013
Location: Evansville, IN
Posts: 10,628
Joe, a Toyota assembly shop typically has only 3 robots, and they all put urethane on windows. Now, weld, paint, plastics, stamping, and powertrain, they got a bunch. Year models aren't usually that much, more like 71-72 Olds than 70-71. A minor model change would be like 70-71 Olds, and we have those every few years on each car. A major model is every 5-8 or so and would be like a 67-68 Olds change.

TK, I think all the Toyota plants typically stop for a week in the summer, and a week in the winter. They give the plant guys 4 days mandatory off then, and those of us with corporate just get a few extra vacation days, because we work the shutdowns. Nothing like it turning Christmas after you've been on the clock for 36 hours.
Koda is online now  
Old January 25th, 2016, 04:01 PM
  #12  
Registered User
 
TK-65's Avatar
 
Join Date: Feb 2009
Posts: 2,039
Our two weeks in July went to one in June and one in August, to eliminating the weeks altogether. My area ran over Christmas too.

In a transmission plant there is not much model year difference. We launch, run it into the ground, balance it out and start new.
TK-65 is offline  
Old January 25th, 2016, 07:24 PM
  #13  
Bfg
Registered User
Thread Starter
 
Bfg's Avatar
 
Join Date: Jan 2012
Posts: 2,056
Thanks for your replies guys. My second question is would a car with this build date have the smaller or larger hole cut in the floor for the 4 speed?
Bfg is offline  
Related Topics
Thread
Thread Starter
Forum
Replies
Last Post
Boiler_81
442
55
September 22nd, 2020 02:05 AM
GEARMAN69
General Discussion
1
May 22nd, 2015 10:58 AM
gmsteve455
General Discussion
11
March 25th, 2014 07:02 PM
1320dragmonza
Tech Editor's Desk
4
August 17th, 2013 04:44 PM
Greg McDonnell
Toronado
1
November 9th, 2008 11:48 AM



Quick Reply: Build date



All times are GMT -7. The time now is 11:24 PM.